11 Aug 2026
Main video
Engineering Report
Detected changes
Continuation of slab and column casting for typical floors, with extensive wooden formwork and metal shoring visible in the front buildings.
Commencement of internal partition masonry using red and cement blocks on the lower floors where formwork has been stripped.
Installation of sanitary piping (PVC pipes) and fire protection systems, along with the laying of orange electrical conduits within the concrete slabs.
Organization of material storage areas and equipment placement (tower and mobile cranes), with stable conditions for the roads surrounding the project.
Progress reading
The visual evidence aligns with the recorded increase in concrete work (+3%), clearly showing the casting of new slabs. Furthermore, photos of internal installations and the start of masonry work support the jump in finishing (+5%) and electromechanical (+5%) percentages.
vs previous visit
بالمقارنة مع الزيارة السابقة، انتقل العمل من مرحلة الهيكل الأساسي في الطوابق الأولى إلى الطوابق المتكررة العليا، مع ظهور واضح لمواد السباكة والكهرباء التي لم تكن موجودة بكثافة في تقرير يوليو.
Expected next milestones
استكمال صب آخر الأسقف الخرسانية للمباني الحالية، التوسع في أعمال اللياسة الداخلية، والبدء في تمديد الأنظمة الرئيسية في الممرات.