11 Jul 2026
Main video
Engineering Report
Detected changes
Continuation of formwork and reinforcement for typical floor columns, with large areas of slabs ready for pouring or recently cast, and intensive use of concrete pumps (red and blue).
Installation of drainage piping (white PVC pipes) and their distribution within the slab reinforcement mesh prior to the pouring process.
Presence of concrete mixer trucks and heavy equipment, with organized storage areas and site labor movement.
Progress reading
The visual evidence aligns with the recorded increase in the concrete works category (+10%), showing the transition from completed foundations to vertical structural growth. Furthermore, photos of ceiling pipe installations support the commencement of progress reporting for the electromechanical works.
vs previous visit
Compared to the photos from the previous visit (June 24), we observe progress in the number of cast columns and an increase in the area of completed wooden formwork for ceilings. Additionally, there is an introduction of casting equipment (pumps) that was not previously visible with the same intensity.
Expected next milestones
Completion of casting for current floor slabs, commencement of masonry work (blockwork) for lower floors, and intensification of mechanical and electrical system installations.