20 Oct 2026
Main video
Engineering Report
Detected changes
The concrete structure of the buildings is complete, with some remaining construction materials on the rooftops.
Progress is underway on electrical and mechanical (HVAC) installations within the units, alongside ongoing plastering and initial wall finishing works.
Progress reading
The images align with the reported completion percentages; the concrete structure appears 100% complete, while the interior photos reflect ongoing activity in finishing works (30%) and electromechanical systems (30%), which explains the notable increase since the previous site visit.
vs previous visit
Compared to the previous visit, there is a 5% increase in finishing works and a 10% increase in MEP works, which is clearly visible in the photos through the completion of HVAC and electrical installations on the interior floors.
Expected next milestones
Completion of final finishing works, installation of electrical and mechanical systems, and commencement of exterior facade works.