HASAAD FRONT
20 Oct 2026

20 Oct 2026

65%Overall▲ +4% · vs previous visit

Main video

Engineering Report

The concrete structure of the project is fully completed, with ongoing progress in interior finishing works and electromechanical systems. The images indicate tangible advancement in internal installations and preliminary wall finishes.
Detected changes
Concrete Structure100%

The concrete structure of the buildings is complete, with some remaining construction materials on the rooftops.

Finishing Works and MEP Systems90%

Progress is underway on electrical and mechanical (HVAC) installations within the units, alongside ongoing plastering and initial wall finishing works.

Progress reading

The images align with the reported completion percentages; the concrete structure appears 100% complete, while the interior photos reflect ongoing activity in finishing works (30%) and electromechanical systems (30%), which explains the notable increase since the previous site visit.

vs previous visit

Compared to the previous visit, there is a 5% increase in finishing works and a 10% increase in MEP works, which is clearly visible in the photos through the completion of HVAC and electrical installations on the interior floors.

Expected next milestones

Completion of final finishing works, installation of electrical and mechanical systems, and commencement of exterior facade works.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +4%
Concrete Works
0%
Finishing▲ +5%
0%
Electromechanical▲ +10%
0%