HASAAD FRONT
25 Apr 2026

Jeddah Waterfront

18%Overall▲ +2% · vs previous visit

Main video

Engineering Report

Significant progress has been achieved in the foundation works of the Hassad Waterfront Apartments project, with the foundation completion rate reaching 73%. Current works are focused on completing the pouring of ground beams and preparing reinforcement steel for columns and neckings, while reinforced formwork continues across extensive areas of the site.
Detected changes
Ground beams and foundations area95%

Completion of casting for large sections of the concrete ground beams, with the internal layout grid clearly visible compared to the previous visit.

Columns and neck columns90%

Reinforcement steel for columns (stubs) is now protruding above the ground beam level across most sectors of the building.

Site preparations85%

Accumulation of timber and construction materials within the concrete bays in preparation for completing the formwork.

Progress reading

The current images align with the recorded increase in the foundations category (+8%), as work has progressed from the stage of pouring individual footings and neck columns (which appeared in the previous visit's photos with concrete pumps present) to the stage of forming ground beams and floor preparation.

vs previous visit

During the previous visit (2026-04-01), foundation pouring was in its early stages with a heavy presence of mixer trucks and concrete pumps. In the current visit, the site shows the completion of underground concrete structures (ground beams), and the outlines of the apartment layouts are beginning to appear clearly.

Expected next milestones

Completion of backfilling between the ground beams, pouring of the ground floor slab, and commencement of formwork and reinforcement for the ground floor columns.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +2%
Concrete Works
0%
Finishing
0%
Electromechanical
0%
Foundations▲ +8%
0%