HASAAD FRONT
8 Mar 2026

Jeddah Waterfront

14%Overall▲ +2% · vs previous visit

Main video

Engineering Report

The reinforced concrete pouring for the entire foundation raft has been completed, with waterproofing and foundation protection works underway, alongside the emergence of column necks above the raft level.
Detected changes
Site flooring (Foundations)100%

Completion of the reinforced concrete pouring for the entire foundation raft and applying a black bitumen insulation layer.

Columns95%

Appearance of concrete column necks at specific heights above the raft level, with ongoing carpentry work for certain elements.

Site perimeter100%

Removal of concrete pumps and mixer trucks that were present during the previous visit following the completion of the pouring process.

Progress reading

The images clearly reflect the progress in foundation completion, rising from 46% to 54%. Work has transitioned from the active pouring phase (documented in previous visit photos) to the concrete curing and waterproofing stage, alongside the commencement of column neck preparation.

vs previous visit

During the previous visit, concrete pouring operations were underway using three pumps and a large number of mixers. In contrast, current images show a quiet site following the completion of pouring, with the concrete now dry and black waterproofing applied across the entire surface of the raft foundation.

Expected next milestones

Commencement of backfilling around the foundations, and completion of formwork and reinforcement for the ground floor/basement columns.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +2%
Concrete Works
0%
Finishing
0%
Electromechanical
0%
Foundations▲ +8%
0%