25 Aug 2026
Main video
Engineering Report
Detected changes
Continuation of formwork and reinforcement for upper floor slabs, with column pouring at various levels; the structure appears complete in several residential blocks.
Significant progress in the construction of external and internal walls using red blocks and cement across the typical floors.
Organization of traffic paths around the buildings, presence of lifting equipment (cranes) and construction materials, with the stability of previously completed foundations.
Progress reading
The photos align with the observed increase in concrete work (+3%), showing ongoing slab and column works, as well as in finishes (+3%), reflected in the accelerated pace of internal and external masonry. The stability of the electromechanical percentage at 10% is explained by the absence of extensive main installations in the current photos.
vs previous visit
Compared to the photos from the previous visit (21-26), we observe an increase in the level of the concrete structure in the front buildings and an expansion of the blockwork wall areas in the middle floors, confirming a positive difference in completion rates.
Expected next milestones
Completion of concrete pouring for the top floor slabs, commencement of internal plastering works, and intensification of mechanical and electrical system installations.