HASAAD FRONT
24 Jun 2026

Jeddah Waterfront

30%Overall▲ +1% · vs previous visit

Main video

Engineering Report

Significant progress has been observed in the project's concrete structural works, with current efforts focused on reinforcing and preparing upper-floor slabs and casting columns. The imagery shows continuous site activity, featuring heavy machinery (concrete pumps) and intensive labor performing steel fixing and formwork.
Detected changes
Roof slab95%

Completion of reinforcement steel laying and distribution of red hollow blocks (Hordi) across large areas in preparation for pouring.

Columns90%

Completion of concrete pouring for a set of columns on the current floor and commencement of formwork and shoring for the remaining columns.

Utilities85%

Installation of plumbing and electrical conduits (PVC) within the ceiling reinforcement grid.

Progress reading

The visual evidence aligns with the recorded 5% increase in the concrete works category, as the project has transitioned from the preparation phase to intensive reinforcement and the pouring of vertical elements. Finishing and electromechanical works remain at 0% due to the structural framework not yet reaching the stage required for their commencement.

vs previous visit

Compared to the previous visit, there is a noticeable shift from the initial column formwork stage to an advanced stage of slab reinforcement using the ribbed slab system (Red Bricks). Additionally, concrete pumps were observed operating on-site, confirming the start of actual pouring operations for the structural elements.

Expected next milestones

Casting current roof slabs, commencing brickwork, and completing the casting of columns for the next floor.

Progress

0%OverallAverage item progress
1/4 completeavg ▲ +1%
Concrete Works▲ +5%
0%
Finishing
0%
Electromechanical
0%
Foundations
0%

Drone Shots

Ground Photography

3D Model