Jeddah Waterfront
Main video
Engineering Report
Detected changes
Extensive reinforcement steel for columns is visible, with wooden formwork (carpentry) installed for a large number of them across the site.
Commencement of wooden shoring and formwork for the ground floor slabs in certain areas.
Presence of concrete pumps on-site, confirming the start of pouring operations for vertical elements.
Progress reading
The current images align with the surge in concrete work from 0% to 13%, clearly showing the transition from the 'ground' phase to the 'vertical' phase. Furthermore, the foundations reaching 89% completion is evident in the finished casting of the ground beams and the commencement of backfilling and preparing the interstitial spaces.
vs previous visit
During the previous visit, the site was limited to ground beam works and foundations within construction trenches without any prominent vertical elements. In the current visit, the site is bustling with standing columns and elevated wooden formwork, reflecting tangible progress in the concrete structure.
Expected next milestones
Completion of the ground floor column casting, and commencement of the steel reinforcement and formwork for the first-floor ceilings.