HASAAD FRONT
20 May 2026

Jeddah Waterfront

26%Overall▲ +8% · vs previous visit

Main video

Engineering Report

The project has seen significant progress in above-ground construction, transitioning from the foundation and ground beam stage to column casting and slab preparation, while continuing to complete the remaining foundation works with a completion rate of 89%.
Detected changes
Structural columns100%

Extensive reinforcement steel for columns is visible, with wooden formwork (carpentry) installed for a large number of them across the site.

Ceilings (Ground floor)90%

Commencement of wooden shoring and formwork for the ground floor slabs in certain areas.

Equipment100%

Presence of concrete pumps on-site, confirming the start of pouring operations for vertical elements.

Progress reading

The current images align with the surge in concrete work from 0% to 13%, clearly showing the transition from the 'ground' phase to the 'vertical' phase. Furthermore, the foundations reaching 89% completion is evident in the finished casting of the ground beams and the commencement of backfilling and preparing the interstitial spaces.

vs previous visit

During the previous visit, the site was limited to ground beam works and foundations within construction trenches without any prominent vertical elements. In the current visit, the site is bustling with standing columns and elevated wooden formwork, reflecting tangible progress in the concrete structure.

Expected next milestones

Completion of the ground floor column casting, and commencement of the steel reinforcement and formwork for the first-floor ceilings.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +7%
Concrete Works▲ +13%
0%
Finishing
0%
Electromechanical
0%
Foundations▲ +16%
0%

Drone Photography

Site Photos

3D Model