Engineering Report
Detected changes
Completion of concrete pouring for all main structural elements of the buildings.
Commencement of internal plastering works and installation of electrical and plumbing conduits within the residential units.
Progress reading
The images confirm the completion of the concrete structure (100%), while images 17-20 highlight progress in finishing works (20%) and electromechanical installations (15%), evidenced by wiring and piping work within the units.
vs previous visit
Compared to the previous visit, the remaining 25% of the concrete structure has been completed, with a slight increase in finishing works and MEP installations due to intensified activity within the floors.
Expected next milestones
Focusing on waterproofing works, completing mechanical system installations, and commencing final finishing works (painting and flooring).