HASAAD FRONT
1 Apr 2026

Jeddah Waterfront

16%Overall▲ +2% · vs previous visit

Main video

Engineering Report

Significant progress has been made in the foundation works of the Hassad Waterfront Apartments project, with the foundation completion rate rising to 65%. Current activities are focused on pouring reinforced concrete for the footings and ground beams using mobile concrete pumps, while carpentry and steel reinforcement work continues across the remaining sections of the site.
Detected changes
Foundations and ground beams area95%

Commencement of reinforced concrete pouring operations with Everdigm concrete pumps and transit mixers on-site

Site flooring90%

Application of waterproofing layers (black bitumen) over extensive areas of plain concrete

Carpentry works85%

Installation of wooden formwork for retaining walls and perimeter ground beams across the site

Progress reading

The visual evidence aligns with the recorded increase in the foundations category (+11%), as work has progressed from the insulation and steel reinforcement phase observed in the previous visit to the actual reinforced concrete pouring phase, explaining the jump in the completion rate.

vs previous visit

Compared to the visit on 2026-03-08, we observe the site's transition from the reinforcement steel preparation phase for the entire area to the partial pouring phase. Previous images showed a dense reinforcement steel mesh covering the site, while current images show the progress of pouring works and the clearer emergence of column necks and ground beams, with active pouring equipment present.

Expected next milestones

Completion of all footings and ground beams casting, commencement of backfilling around the foundations, and preparation for the ground floor concrete works.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +3%
Concrete Works
0%
Finishing
0%
Electromechanical
0%
Foundations▲ +11%
0%