Jeddah Waterfront
Main video
Engineering Report
Detected changes
Execution of large-scale excavation works and reaching the initial foundation depth in parts of the site
Installation of security fencing around the entire work area and setting up entry and exit gates
Assembly and stockpiling of timber and metal formwork quantities adjacent to the excavation area
Accumulation of excavated soil and sub-base gravel piles in preparation for leveling operations
Progress reading
Visual observations align with the reported foundation completion rate (32%), as a significant portion of excavation and site preparation work has been finished. The absence of any concrete structures or utility installations confirms the accuracy of the 0% completion rates for concrete, electromechanical, and finishing works.
vs previous visit
There is no previous visit for comparison; this report serves as the project baseline.
Expected next milestones
Completion of excavation works, commencement of blinding concrete pouring, and delivery of reinforcement steel for the foundations.