HASAAD FRONT
13 Jan 2026

Jeddah Waterfront

8%Overall▲ +5% · vs previous visit

Main video

Engineering Report

Initial phase works have commenced for the Hassad Waterfront Apartments project, with current activities focusing on site preparation, excavation, and foundation leveling. The images show heavy machinery (excavators and transport trucks) actively operating on-site, alongside the completion of site fencing and the stockpiling of timber and equipment required for the upcoming stages.
Detected changes
Main excavation area100%

Execution of large-scale excavation works and reaching the initial foundation depth in parts of the site

Site perimeter100%

Installation of security fencing around the entire work area and setting up entry and exit gates

Storage and staging area95%

Assembly and stockpiling of timber and metal formwork quantities adjacent to the excavation area

Site ground90%

Accumulation of excavated soil and sub-base gravel piles in preparation for leveling operations

Progress reading

Visual observations align with the reported foundation completion rate (32%), as a significant portion of excavation and site preparation work has been finished. The absence of any concrete structures or utility installations confirms the accuracy of the 0% completion rates for concrete, electromechanical, and finishing works.

vs previous visit

There is no previous visit for comparison; this report serves as the project baseline.

Expected next milestones

Completion of excavation works, commencement of blinding concrete pouring, and delivery of reinforcement steel for the foundations.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +6%
Concrete Works
0%
Finishing
0%
Electromechanical
0%
Foundations▲ +22%
0%

Drone Photos

Site Photos

3D Model