7 Oct 2026
Main video
Engineering Report
Detected changes
The concrete structure of the buildings is fully complete, with masonry works ongoing on the upper floors.
Internal electrical and mechanical installations (conduits and cabling) have commenced on the floors where concrete work is finished.
Progress reading
The images align with the reported completion rates, showing the concrete structure fully finished (100%), while internal images (17-20) reflect the advancement of electromechanical and preliminary finishing works, both of which have increased by 5%.
vs previous visit
Compared to the previous visit, work on interior finishes and installations is clearly progressing, while the concrete structure remains unchanged as it was previously completed.
Expected next milestones
Completion of interior plastering works, commencement of plumbing installations, and initiation of roof waterproofing.