Jeddah Waterfront
Main video
Engineering Report
Detected changes
Execution of large-scale excavation works for foundations, with groundwater or rainwater accumulation observed at the bottom of the pit
Installation of security fencing around the entire work area and preparation of entry and exit gates
Arrival and stockpiling of timber and raw materials required for early formwork activities
Presence of hydraulic excavators and earth-moving trucks on-site to commence operations
Progress reading
Visual observations align with the declared foundation completion rate (10%), as works are still in the excavation and leveling phase, and concrete pouring has not yet commenced (0%). The presence of timber materials indicates preparations to begin formwork for the footings once excavation and shoring are completed.
vs previous visit
There is no previous visit for comparison
Expected next milestones
Dewatering of excavations, pouring of plain concrete (blinding), and commencement of reinforcement and formwork for the footings.