HASAAD FRONT
8 Jan 2026

Jeddah Waterfront

3%OverallFirst visit — no previous comparison.

Main video

Engineering Report

Initial phase works have commenced for the Wajhat Hassad Apartments project, with current activities focused on site preparation and primary foundation excavations. The images clearly show the completion of site fencing and the presence of heavy machinery to begin excavation and ground leveling works.
Detected changes
Main excavation area100%

Execution of large-scale excavation works for foundations, with groundwater or rainwater accumulation observed at the bottom of the pit

Site perimeter100%

Installation of security fencing around the entire work area and preparation of entry and exit gates

Material storage area95%

Arrival and stockpiling of timber and raw materials required for early formwork activities

Equipment100%

Presence of hydraulic excavators and earth-moving trucks on-site to commence operations

Progress reading

Visual observations align with the declared foundation completion rate (10%), as works are still in the excavation and leveling phase, and concrete pouring has not yet commenced (0%). The presence of timber materials indicates preparations to begin formwork for the footings once excavation and shoring are completed.

vs previous visit

There is no previous visit for comparison

Expected next milestones

Dewatering of excavations, pouring of plain concrete (blinding), and commencement of reinforcement and formwork for the footings.

Progress

0%OverallAverage item progress
0/4 complete
Concrete Worksnew
0%
Finishingnew
0%
Electromechanicalnew
0%
Foundationsnew
0%