18 Feb 2026

Jeddah Waterfront

12%Overall▲ +1% · vs previous visit

Main video

Engineering Report

During the current visit, intensive activity was observed in the reinforced concrete pouring for the foundation raft. Concrete pumps and transit mixers are on-site to complete this vital stage, bringing the foundation completion rate to 46%.
Detected changes
Raft Foundation Area100%

Commencement of ready-mix concrete pouring and covering extensive areas of reinforcement steel with concrete

Site Perimeter100%

A lineup of numerous concrete mixers and the deployment of two concrete pumps

Reinforcement Works95%

Continued visibility of column rebar starters above the current pouring level

Progress reading

The visual evidence aligns with the recorded increase in the foundations category (+3%), as work has transitioned from the full reinforcement stage (visible in previous photos) to the actual concrete pouring phase. This explains why structural concrete percentages remain at 0% pending the complete finalization of the foundations.

vs previous visit

Compared to the photos from the previous visit (2026-02-16), the site was focused on rebar work for the raft foundation, whereas current photos show the commencement of actual pouring operations and the presence of heavy pouring equipment, reflecting tangible progress in the foundation timeline.

Expected next milestones

Completion of the entire raft foundation pouring, commencement of foundation waterproofing, followed by the shuttering and reinforcement of the ground floor columns.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +1%
Concrete Works
0%
Finishing
0%
Electromechanical
0%
Foundations▲ +3%
0%

Drone Photography

Site Photos

3D Model

ShareChat on WhatsApp