Jeddah Waterfront
Main video
Engineering Report
Detected changes
Commencement of ready-mix concrete pouring and covering extensive areas of reinforcement steel with concrete
A lineup of numerous concrete mixers and the deployment of two concrete pumps
Continued visibility of column rebar starters above the current pouring level
Progress reading
The visual evidence aligns with the recorded increase in the foundations category (+3%), as work has transitioned from the full reinforcement stage (visible in previous photos) to the actual concrete pouring phase. This explains why structural concrete percentages remain at 0% pending the complete finalization of the foundations.
vs previous visit
Compared to the photos from the previous visit (2026-02-16), the site was focused on rebar work for the raft foundation, whereas current photos show the commencement of actual pouring operations and the presence of heavy pouring equipment, reflecting tangible progress in the foundation timeline.
Expected next milestones
Completion of the entire raft foundation pouring, commencement of foundation waterproofing, followed by the shuttering and reinforcement of the ground floor columns.