HASAAD FRONT
3 Nov 2026

3 Nov 2026

66%Overall▲ +1% · vs previous visit

Main video

Engineering Report

The current site visit shows a slight progress of 2% in both finishing works and electromechanical systems, while the concrete structure and foundations remain at 100% completion.
Detected changes
Finishing32%

Interior finishing works are ongoing, with plastering visible in some rooms and ceramic tile installation in bathrooms, alongside continued electrical and mechanical installations.

Electromechanical32%

Electrical and mechanical installation works continue within the residential units, with new materials delivered to the site.

Structural Framework

The structural framework is fully complete, with no new structural changes compared to the previous site visit.

Progress reading

The photos align with the reported progress percentages, as work is currently focused on finishing and electromechanical items (32%), while structural works (concrete and foundations) remain at 100%.

vs previous visit

Compared to the previous site visit, there are no fundamental changes to the building's exterior structure; however, there is tangible progress in the pace of interior finishing works and technical installations within the units.

Expected next milestones

Completion of interior finishing works (plastering, painting, flooring) and intensification of electromechanical installation works on the remaining floors.

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +1%
Concrete Works
0%
Finishing▲ +2%
0%
Electromechanical▲ +2%
0%
Foundations
0%