Jeddah Waterfront
Engineering Report
Detected changes
Commencement of pouring the lean concrete (blinding) layer, covering a significant portion of the foundation area.
Presence of a concrete pump and several mixing trucks in operational status on-site.
Organization and preparation of timber and materials required for reinforced formwork.
Progress reading
Although the foundation percentage remains steady at 32% in the digital report, the images show a physical transition from the leveling and excavation stage seen in the previous visit to the pouring stage, indicating tangible progress in the preparatory works for the footings.
vs previous visit
During the previous visit (2026-01-13), the excavation contained piles of soil and gravel with groundwater/surface water in some parts, whereas in the current visit, the site has been cleared and the concrete blinding layer has been poured in an organized manner.
Expected next milestones
Completion of blinding concrete pouring, commencement of waterproofing works, followed by the start of reinforcement and formwork for the reinforced footings.