HASAAD FRONT
2 Feb 2026

Jeddah Waterfront

8%OverallFirst visit — no previous comparison.

Engineering Report

Intensive construction activity was observed on-site during the current visit, as blinding concrete pouring for the foundations has commenced across large areas of the project site, with a continuous presence of pouring equipment and ready-mix concrete trucks.
Detected changes
Project Site - Excavation100%

Commencement of pouring the lean concrete (blinding) layer, covering a significant portion of the foundation area.

General Site100%

Presence of a concrete pump and several mixing trucks in operational status on-site.

Staging Area95%

Organization and preparation of timber and materials required for reinforced formwork.

Progress reading

Although the foundation percentage remains steady at 32% in the digital report, the images show a physical transition from the leveling and excavation stage seen in the previous visit to the pouring stage, indicating tangible progress in the preparatory works for the footings.

vs previous visit

During the previous visit (2026-01-13), the excavation contained piles of soil and gravel with groundwater/surface water in some parts, whereas in the current visit, the site has been cleared and the concrete blinding layer has been poured in an organized manner.

Expected next milestones

Completion of blinding concrete pouring, commencement of waterproofing works, followed by the start of reinforcement and formwork for the reinforced footings.

Progress

0%OverallAverage item progress
0/4 complete