17 Nov 2026
Main video
Engineering Report
Detected changes
Interior finishing works are ongoing, with electrical and mechanical conduits being installed in the ceilings and plastering works commencing in select rooms.
Installation of HVAC ductwork and plumbing drainage systems within the concrete ceilings is underway, with materials currently staged on-site.
The structural framework for all buildings is fully complete, with no further structural construction works remaining.
Progress reading
The images reflect a slight progress of 2% in both finishing and MEP works, which aligns with the visible internal installations and initial plastering works in the residential units.
vs previous visit
Compared to the previous visit, there are no fundamental changes to the concrete structure; however, current photos show an increase in the density of mechanical and electrical installations within the units, along with notable progress in interior plastering works.
Expected next milestones
Completion of electromechanical installation works, commencement of waterproofing and thermal insulation for roofs, and an increased pace of final finishing works (painting, flooring).