HASAAD FRONT
17 Nov 2026

17 Nov 2026

67%Overall▲ +1% · vs previous visit

Main video

Engineering Report

The HASAAD FRONT project site was visited on 2026-11-17, showing ongoing finishing works and MEP systems with an overall completion rate of 67%. The concrete structure is fully complete, and current efforts are focused on internal installations and architectural finishes.
Detected changes
Finishing34%

Interior finishing works are ongoing, with electrical and mechanical conduits being installed in the ceilings and plastering works commencing in select rooms.

Electromechanical34%

Installation of HVAC ductwork and plumbing drainage systems within the concrete ceilings is underway, with materials currently staged on-site.

Structural Framework

The structural framework for all buildings is fully complete, with no further structural construction works remaining.

Progress reading

The images reflect a slight progress of 2% in both finishing and MEP works, which aligns with the visible internal installations and initial plastering works in the residential units.

vs previous visit

Compared to the previous visit, there are no fundamental changes to the concrete structure; however, current photos show an increase in the density of mechanical and electrical installations within the units, along with notable progress in interior plastering works.

Expected next milestones

Completion of electromechanical installation works, commencement of waterproofing and thermal insulation for roofs, and an increased pace of final finishing works (painting, flooring).

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +1%
Concrete Works
0%
Finishing▲ +2%
0%
Electromechanical▲ +2%
0%
Foundations
0%